Hi I am creating a change request process workflow as per below requirement. I am facing issue at dependent activity stage. The activities in Release record are actually not starting automatically. When i open the release record and click on Run then everything works perfect. I want to avoid this manual intervention in my workflow. Further i want to know that what are the other activities those can work with Dependent activity, I mean Review etc.
I have configure the Activities as below:
CHANGE REQUEST
02 Separate Review Activities for Approval> Then> Dependent Activity with Linked to Release Record and Then one Manual Activity.
RELEASE RECORD
01 Manual Activity for Test, 01 RA for Approval Pre-Production, Then 01 MA for Pre-Production deployment.