Microsoft Project Server Issue assigning value to a Cost Resource

Dear Microsoft:

I have an issue using Microsoft Project 2010 . 

I need to assign a value to a cost resource but when I type the correspondent value in the Assign Resources Template, then press enter, the value of the resource ($700) is automatically set to 0.00.

Here is the assign resources template.  I type the value of 700

Then press enter and the value is automatically reset to zero.

So, the value appear as 0.00 in the table of costs.

Please help me with this situation.

Thanks so much.

Vernica

July 17th, 2015 2:42pm

Hi,

Do you mind sharing us a sample file or send it to us (ibsofc@microsoft.com)? We can test it and assist you better.

Regards,

George Zhao
TechNet Community Support

Free Windows Admin Tool Kit Click here and download it now
July 21st, 2015 1:42am

This topic is archived. No further replies will be accepted.