Exchange 2007 : User assigns task to another user - will updates be present on both users Task items?
Hi, I am trying to figure out if it is possible in Exchange 2007 to get the following to work. Assume we have User1 and User2. User1 adds an item in his Task list. The next day he needs to assign this to User2 since he can not complete the Task. He forwards the Task to User2. If User2 now would Complete the Task, will that information get back into the Task item present on User1's Task list in Outlook? They are both on the same Exchange 2007 system. Sincerely, Andreas
May 5th, 2011 4:25am

Yes. You don't forward but assign the task. When user 2 complete the task they must update the progress and then it should prompt to send an update back to User 1. Sukh
Free Windows Admin Tool Kit Click here and download it now
May 5th, 2011 5:21am

Yes. You don't forward but assign the task. When user 2 complete the task they must update the progress and then it should prompt to send an update back to User 1. Sukh Sounds great! It seems though that the functionality of Assigning to another person is not present when running OWA. Sincerely, Andreas
May 5th, 2011 6:57am

Assigned tasks cannot be modified using Microsoft Outlook Web Access. To modify an assigned task, use a different program, such as Microsoft Office Outlook.
Free Windows Admin Tool Kit Click here and download it now
May 5th, 2011 7:01am

This topic is archived. No further replies will be accepted.

Other recent topics Other recent topics