Archive Project in project server 2013 using daily Schedule backup,
I just wanted to know the default value for retention policy in project server if it is not set by us.
- Edited by Harshal7689 55 minutes ago
Technology Tips and News
Archive Project in project server 2013 using daily Schedule backup,
I just wanted to know the default value for retention policy in project server if it is not set by us.
Hi Harshal
You can see here
Value of retentionPolicy |
Description |
---|---|
> 0 |
Set the project retention policy; override the Project Server default retention policy. |
0 |
Unlimited retention. Archive the project and do not check for retention delete. |
-1 |
Use the project policy if it is set, otherwise use the Project Server default. |
-2 |
Use the Project Server default retention policy and clear the project retention policy. |