What are peoples recommendations for managing part time resources?
Any guidance/tips on how to best manage part time resources in PWA2013 would be greatly appreciated.
September 14th, 2015 10:52am

Hi Kev,

I would amend the resource calendar to reflect their working hours in total, but I don't tend to reflect the actual start time - it's just too much micro management.  For example, if a user works 20 hours per week, then I'll just set up 08:00 to 12:00 each day, rather than say 10-12:00 and then 13:00-15:00.  Keeping the start time @ 08:00 keeps the Gantt chart formatting nice :)