This list cannot be displayed as a Gantt chart because it lacks required fields Due to Calculated Due Date Field
Hello All,I am lookig for a solution to use a calculated date column for my Due Date in a Gantt View.Thanks in advance for any help :)Bob HansonBobH
February 13th, 2010 5:33am

Hi Bob Hanson, It should be a known issue that calculated field isn’t intended to be supported in the Gantt View even they display in the list of fields you can choose. Sorry for the inconvenience. Best Regards. Lily Wu
Free Windows Admin Tool Kit Click here and download it now
February 16th, 2010 6:42am

Hi, Please point out the source location for this information. Thank you!
March 24th, 2010 3:51am

This topic is archived. No further replies will be accepted.