Tasks will not slide in time according to dependencies
Hi! I have this problem in MS Project that a milestone that is set up as Auto Schedule with a dependency to a task that finish 14th January place itself at 18th December. How is this possible? The Constraint of the milestone is "As Soon As Possible". I have similiar problems with several tasks and milestones in the same plan. I have not used MS Project in some years but used it quite a lot earlier. Can not remember this problem from previous days.
July 29th, 2015 3:46am

This topic is archived. No further replies will be accepted.