My MSP 2013 schedule has some activities linked with SS and FF with lag. When I sync with Ssharepoint 2013, linkages and lags not get reflected in sharepoint. Do we have any solution to reflect these relationships in sharepoint?

regards

a

August 17th, 2015 7:27am

Hi,

MSP 2013 is Microsoft Project 2013. Is it right?

SharePoint does not directly support the different predecessor types (e.g. Finish-to-Finish, Start-to-Start) and task dependencies, such as Lead and Lag times, any impact on dates (Start, Finish etc.) are fully reflected in SharePoint.

More information, please refer to the link:

http://www.manageprojectsonsharepoint.com/blog/2013/05/13/the-improved-sharepoint-2013-to-project-sync/

http://blogs.technet.com/b/projectsupport/p/ps13cu.aspx

As this issur is about Project, I suggest you create a new thread on Project forum. The reason why we recommend posting appropriately is you will get the most qualified pool of respondents, and other partners who read the forums regularly can either share their knowledge or learn from your interaction with us. Thank you for your understanding.

Project forum:

https://social.technet.microsoft.com/Forums/projectserver/en-US/home?category=project

Thanks,

Wendy