Hi All, I have Project tasks and Issue Tracking. Column called projects added to Project tasks and using projects column in Issue Tracking as a Look Up. Now my Question is I am unable to see connections option under project tasks when I edit the web part i.e. it is not showing further options to connect Issue Tracking. I can see the option for Issue Tracking but not for Project Tasks. How Can I make it work.
April 27th, 2010 9:04pm

Is this in a PWA site? Project Web Access or SharePoint..Kris Wagner, MCITP, MCTS Twitter @sharepointkris Blog: http://www.sharepointkris.com/blog
Free Windows Admin Tool Kit Click here and download it now
April 27th, 2010 11:17pm

I have found the answer by myself. It will not support web part connections. In order to achieve we need to use sharepoint designer and then use custom list form and you will be able to connect the web parts.