Hi All.
We are experiencing an issue that the OoO times from exchange is not synced with project resource.
I have enabled the out of office sync feature in "sharepoint central administration" and also enabled a few resources for the OoO Sync.
Now when i'm assigning a task to a resource which shouldn't be available i cannot see that this resource is not available.