Number of precedence constraints
Hi, I need to export data to a file depending on a condition. So I have a fork based on the condition. After creating the file I want to make some more processes with it (zip, mail, archive) no matter what the earlier condition was. Because of this one of the tasks has 2 incoming precedence constraints (green arrows), but nothing is executed after the fork. What do I do wrong? --->Task A --> Condition 'Not running tasks' --->Task B --> Thanks. P.
June 6th, 2012 11:58am

You need to right click on the constraint - click EDIT and make it an OR. Then the lines going into that block will be dashed - indicating an OR condition Chuck Pedretti | Magenic North Region | magenic.com
Free Windows Admin Tool Kit Click here and download it now
June 6th, 2012 12:01pm

That was simple, thanks! :)