Found an issue rescheduling tape jobs in DPM 2010

Scenario: Tape jobs are scheduled for today. I can see them by running a report in 'Monitoring' - 'Jobs'- 'Scheduled Tape Jobs'

I see I have too many tape jobs all scheduled for the same time. Normally this isn't an issue, but since the jobs are so big the ones waiting will randomly fail. Had the idea of moving them to a new time slot same day.

Selected a PG that was slated for Tape Backup, edited the time window of when it would run today. Saved changes everything confirms.

Went back to 'Monitoring' - 'Jobs'- 'Scheduled Tape Jobs', its now missing from the list. I didn't change the day it was going to run and I didn't set the time to a value that has already expired. Job was originally scheduled for 11PM today, I set it to 5pm today instead. 

Any explanation ?


September 1st, 2015 11:40am

This topic is archived. No further replies will be accepted.