Fix a task to a start time

Hi Everyone,

Im trying to fix a task to a start time except I want it to start to a lag and not a 24 hour clock.

For example, I want a task to start 16 hours from the beginning of a 50 hour set of work. I have done this using the lag method (4FS + 16 hrs, Where 4 is astarting cell)

For ease of management it has to start after 16 hours but when I level it, it moves to where Project sees fit.

Please could someone help in fixing the lag?

Thanks

Alex

March 31st, 2015 3:20am