There are five jobs in the sql server agent in the FIM portal database created by the installation i presume. Two (FIM_MaintainGroupsJob, FIM_MaintainSetsJob) are not enabled. Do these jobs need to be enabled for the groups and sets to be updated. Should these be enabled in production?
July 1st, 2010 5:19pm

The FIM_MaintainGroupsJob has two steps 1) EXEC FIM.MaintainSets 2) EXEC FIM.MaintainGroups The FIM_MaintainSetsJob has one step 1) EXEC FIM.MaintainGroups The FIM_TemporalEvents Job which is scheduled has four steps. Steps two and three are to run those same stored procedures. So those two jobs don't need to be scheduled because the FIM_TemporalEvents Job is and executes the same things.David Lundell www.ilmBestPractices.com