Assigning resources in Project Server 2013

Hi,

Is it possible to assign a resource to a task through PWA in Project Server 2013?

I have a created a project in PWA, built team,saved and published but can't assign resources.

Do i need to open Project Professional to assign the resources?

October 7th, 2013 6:25am

Hello,

Yes you can assign resources using PWA. Once you have built the team, saved and closed the build team page, you will be able to click the Resource Name cell for a task and the drop down menu will show the resources you have added to the team. Add the required resources. You do not need Project Pro to assign resources.

Paul

Free Windows Admin Tool Kit Click here and download it now
October 7th, 2013 8:15am

Hi Paul,

Would you be able to provide an example of how to setup the teams, resources and tasks so that is possible? I am currently trying to implement the type of resource selection that you are referring to and I'm having some difficulty getting to the point where I can filter down the resources available to be assigned to the task.

Ideally I'd like to be able to limit the resources available for assignment to the task based on the skills required for the task and the skills assigned to the resource but there doesn't seem to be an easy way to set it up with Project Server 2013 and Project Professional 2013.

Thanks in advance

-edejonge

January 31st, 2014 8:01pm

Make sure that least one group that you are assigned to has the permission to assign resources.   Some companies manage permissions and only allows the resource manager to make task assignments.

cheers

Free Windows Admin Tool Kit Click here and download it now
February 2nd, 2014 9:03pm

Hi,
Is it possible to assign partially resources through PWA in Project Server 2013?

Thanks!


May 30th, 2014 3:23pm

I think you will find you can, unless I have misunderstood... Add the "Units" field to one of the Project Assignment PWA views. This field is only available for Project PWA views based on the Assignment table. You can then change the units for the assignments in PWA.

Paul

Free Windows Admin Tool Kit Click here and download it now
May 30th, 2014 3:34pm

Is it possible that the Units field in those views is not syncronised with work and duration values?

As an example, I have created a task an added one resource. The systems calculates work hours, i.e, 120h (task is fixed duration type and Effort driven). The I add a new resource to the task, so that I expect that both resources will work 50%.

But when switching to a Project Assignment View, it is still showing 100% units for both resources, although the work hours are right (each one has half of the initial hours: 60 + 60)

Thanks!

July 8th, 2014 1:11pm

Hi Jos,

This behavior is normal. See my example below with 1 resource on a fixed duration and effort driven task:

If I add a second resource, the duration is fixed so it will not change. The task is effort driven so the total effort will be kept at 40h, but splitted between the 2 resources:

The units will still be 100%, the assignment unit behavior has significantly changed in Project 2010, see references below:

  • http://blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx
  • http://ntrajkovski.com/2012/11/20/units-and-peak-units-in-ms-project-2010-what-are-they/

If you insert the peak column in the task usage view, you'll see that the % unit for the 2 assignments ar

Free Windows Admin Tool Kit Click here and download it now
July 8th, 2014 1:26pm

Final screenshot with the peak unit:

July 8th, 2014 1:28pm

Thanks a lot for your response Guillaume!

It helped me very much to understand where I have to look at.

I am trying to establish a sequence of steps for some people doing draft plans and demanding resources, using PWA. They first use a PWA task view to set task durations and generic resources needed. When some tasks require different profiles or profiles are not needed 100%, we need them to refine the effort of each resource, whether by setting units or work. This has to be done by a PWA Assignments view.

But I cannot find the Peak field in none of them. It seems it is one of the limitations of PWA...

Regards,

Jose

Free Windows Admin Tool Kit Click here and download it now
July 8th, 2014 3:20pm

The peak field is a calculated field so not editable in PWA. You could rather fix the duration and update the work.

For example for a single task lasting for 40 days with 4 resources at 25%, edit the work field in an assignment view and enter 10d (40d*25%) for each assignments. I'd suggest to deal with the work rather than with the % unit.

July 8th, 2014 3:38pm

hi Guillaume Rouyre,

another question, How can I open the webpage you shown. 

Our user first use pwa-task schedule to set task and resource.

/Jou Chen

Free Windows Admin Tool Kit Click here and download it now
April 3rd, 2015 7:48am

Hi Jou Chen,

What is exactly your question, concern? My screenshots are from MS Project Pro, not PWA.

Please tell me more so I can help you.

April 3rd, 2015 7:56am

hi Guillaume,

here is my situation:

A engineer, he join 2 projects(P_A,P_B) in same time , I want to set tasks to him ,  P_A use 40% on 4/7 , and P_B use 60% on 4/7 , can I setting like this in PWA?

And  can I set alarm while use rate over 100% or over 8 hours?


Free Windows Admin Tool Kit Click here and download it now
April 6th, 2015 10:19pm

Hi

You cannot predefine the %unit per resource on a project. But you can mention in PWA the %unit of a resource on an assignment in the project, using the unit column in a PWA view.

April 7th, 2015 3:27am

This topic is archived. No further replies will be accepted.

Other recent topics Other recent topics